Our Civil Engineering Executed Projects

SERS Structural Engineering Consulting Dubai currently has a main activity  that has a solid component related to the production of structural engineering in detailed design phases for bridges construction structures, civil engineering work and underground work, particularly in Dubai and on the Grand Paris Express construction sites and various road or rail projects in mainland France and more generally in Europe. You will surely find in the rest of this section a non-exhaustive list of our current or completed projects.

Well P04 « Parc Robespierre » – Line 15 South Lot T3C

Civil Engineering of Well P04: Parc Robespierre in Paris The appendix OA-P04 Well is located in « Parc Robespierre». This

Chatillon Montrouge Station – Line 15 South Lot T3C

Structural Engineering Project: Châtillon Montrouge Station The Chatillon-Montrouge station is a 110m long and 27m wide station of the T3C

Highway Bypass in the West of Strasbourg A355

Civil Engineering Construction: Highway Bypass in Strasbourg Supplied by high-quality equipment, SERS' team of qualified civil engineering construction in Dubai ensured a

The Extension of line 12 North – « Aime Cesaire» Station

Civil Engineering Construction: Extension of Aime Cesaire Station France The subway line 12 project consists of the extension of the

Extension of Line 4 South – Verdun Access

Civil Engineering Project: Extension of Line 4 South Verdun Access The civil engineering construction project of Line 4 subway consists

Line 15 South Lot T3C – « Villejuif Gustave Roussy » Station

Stuctural Engineering Construction Project: Line 15 South Villejuif Station The « Villejuif Gustave-Roussy » station is one of the most

« Port De Calais » – Underpasses OA5 & OA6

Construction Project: Underpasses OA5 & OA6 in Port de Calais The construction of a new 90 hectares deep-water basin, the

Doubling of the « Viaduc Du Cher » Bridge

Construction Project: Doubling Viaduc Du Cher Bridge A85 development project. The purpose of this bridge construction project to allow the

Line 14 South – Lot GC02 – « Kremlin Bicêtre » Station

Construction Project: The Extension Line 14 South Kremlin Bicêtre Station The structural engineering consultants of SERS take charge of the construction of

Foot Bridge in « Gare D’Albert » – Conception of the Steel Walkway Structure

Construction Project: Conception of the Steel Walkway Structure The purpose of this bridge conception project is construct to of a new

Doubling of the RER C Tunnel – « Tunnel de Meudon »

Construction Project: The Doubling of the RER C Tunnel The following construction project involves a gallery and two branches. To

Strassen Bypess – Bridge Conception (Underpasses And Viaduct)

Bridge Construction Project: Conception of Underpasses And Viaduct This project of bridge construction consists of construction of a high-level link,

Tertiary Building – « Operating And Maintenance Center »

Construction Project: Tertiary Building Champigny-sur-Marne This project of civil engineering construction consists of building an approximately 85m long shaft in

Extension of Line B – « Metro De Lyon »

Structural Engineering Project: Extension of Line B in Lyon Station This structural engineering conception project consists of the extension of

Line 15 Lot T3C – « Arcueil Cachan » Station

Civil Engineering Project: Arcueil Cachan Station Extension This civil engineering project consists of the extension of line 15 over a surface

Epure – Teutatès Phase 2

Civil Engineering Construction Project: Epure Installation France The civil engineering consultants of our construction company Dubai take charge of the building operation of

Maintenance And Storage Site – Morangis

Construction Project: Line 14 South Morangis The civil engineering consultants of SERS take charge of the construction of the Morangis station project. This project

Metro – Line M4 (Sydhavn) – « SLU & GAB » Stations

Civil Engineering Project: Extension of Line M4 in SLU & GAB Stations This civil engineering conception project consists of the

Seine Aval Unit Production Construction

Construction Project: Unit Production Seine Aval At SERS, our structural engineering consultants, ensure the execution of building engineering solutions of

Claude Monet Middle School Construction

Civil Engineering Project: Claude Monet Middle School The structural engineering consultants of our construction engineering Dubai take charge of the construction of a

The « Epinay-Sur-Orge » Rail Bridge

Construction Project: The «Epinay-Sur-Orge » Rail Bridge The bridge construction engineering consultants of SERS create and ensure the construction of the «

Underground Construction – “Chute De Romanche Gavet”

Engineering Consulting: Underground Gallery Construction An expert structural engineering consultant Dubai, along with his team of professional engineers created and

“Rennes” Subway Line B – “Gros Chêne” Station

Engineering Consulting Project: Gros Chêne Station The competent engineers of our engineering consulting company Dubai created and ensured a practical

Etihad – Phase 2 of the Water Railway

Structural Engineering Project: Etihad Water Railway The engineering consultants of SERS were entrusted with the construction of the Etihad Water Railway network in Dubai. This network,

Line 13 – Interconnection “Chatillon Montrouge” Station

Construction Engineering Consulting: Station Interconnection A qualified construction engineering consultant Dubai of our team of engineers took charge of the civil engineering project

Line 18 Phase 1 – Tender Phase

Construction Engineering Project: Stations Connection SERS' construction engineering consultants executed the tender phase of line 18 and the connections of a number of stations

Railway Construction – ATM – M10VP

Civil Engineering Consulting: Railway Construction An expert civil engineering consultant Dubai took charge of the railway  construction consulting. Our mission is focused on the M10VP

LINE 16 – « LA COURNEUVE SIX ROUTES » STATION

The future metro station is a station of the tramway line 1 of the Ile-de-France tramway (line T1) located on

EOLE – « CNIT » STATION

The construction of a new underground station 30m deep, one kilometre of tunnels linking the new station to « Courbevoie

« COEUR DE JOUY »

The construction of 28 apartments, including 8 social housing units, as well as shops at the foot of the building.

« TUNNEL DE MEUDON » – DOUBLING OF THE RER C TUNNEL

The construction of a gallery and two branches. Improving evacuation conditions for users of the « Tunnel de Meudon »

DARD BRIDGE

The Dard bridge is a straight VIPP-type road structure, 31.72 m long and with a 7% gradient, carrying the RN205

« LA PASSERELLE DE LA MARE »

The reconstruction of the Mare footbridge. The new footbridge will allow this section of the inner ring road to be

ILOT 3H – ZAC IVRY

The project is mainly located near the Quai Auguste Deshaies. It will include the programs below: Activity or catering areas

ITER Project – TOKAMAK

SERS also works on nuclear projects such as ITER (intervention on 3D reinforcement under TEKLA): The main building is intended

« CHATOU » – COLLECTIVE HOUSING BUILDING

The operation includes the construction of a building complex of 42 social rental housing units of the G+1 to G+2

NEW BRIDGE OF THE « SAINT-DENIS » RIVER

The structure will be 2*2 lanes, will have a TCSP lane in the incoming direction, and lanes for soft modes.

CDG EXPRESS – LOT C – COVERED AND OPEN TRENCH

CDG Express is a 32 km rail link project (including 8 km of new track) in the « Île-de-France »