The construction of a gallery and two branches.

Improving evacuation conditions for users of the « Tunnel de Meudon » by creating a gallery and two branches connecting it to the existing tunnel in order to provide two emergency exits in case of fire.

Contracting authority: SNCF

Project management: INGEROP

Issuer: SPIE Batignolles

Start date: 2018

Phase: Detailed design phase of projects

City : Meudon

Our Missions :

  • Carrying out calculation missions (modelling and calculation notes)
  • Carrying out calculation missions (modelling and calculation notes)
  • Carrying out methodological studies for the opening of the connection branch to the existing tunnel
  • Realisation of formwork drawings,
  • Realisation of reinforcement drawings.